Vivanti Residences by Meteora
Vivanti Residences by Meteora is a building project in Jumeirah Village Circle, Dubai, by Meteora Elite Real Estate Developments. The Dubai Land Department's register puts it at 0.02% complete (not started), with planned completion on Jan 1, 2028.
Planned completion: Jan 1, 2028. Time left: 1 year 2 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3449), which also shows the latest inspection date and photos.
Facts
- Status
- Not started
- Official progress
- 0.02%, as published by the Dubai Land Department
- Planned completion
- Jan 1, 2028
- Construction start
- Jan 1, 2025
- Units
- 476
- Buildings
- 1
- Developer
- Meteora Elite Real Estate Developments
- Master developer
- Nakheel .(P J S C)
- Community
- Jumeirah Village Circle, in DLD's area Al Barsha South Fourth
- Escrow bank
- Abu Dhabi Commercial Bank
- DLD project number
- 3449
The register describes it as: "Residential / Commercial Building (B +G+3P+11 Typical + R & B +G+3P +17 Typical + R & B +G+3P+11 Typical + R)"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 0.02% | Jan 1, 2028 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
45 off-plan sales in Vivanti Residences by Meteora have been registered with the Dubai Land Department, worth AED 43.1 million in all, the first on Jul 22, 2025 and the latest on Nov 5, 2026. 6 of them in the last 90 days. The median price over the last 12 months was AED 16,724 per square meter (AED 1,554 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Jumeirah Village Circle
- Serenz by Danube Jumeirah Village Circle · Danube 0.08%Planned completion Dec 31, 2029
- Auresta Tower Jumeirah Village Circle · Tiger 4.44%Planned completion Dec 31, 2028
- Binghatti Circle Jumeirah Village Circle · Binghatti 22.1%Planned completion May 31, 2027
- Elitz 2 by Danube Jumeirah Village Circle · Danube 20.01%No planned date in the register
- Maimoon Gardens Jumeirah Village Circle · Fakhruddin 78.02%Planned Dec 31, 2025, 10 months ago
- Binghatti Amberhall Jumeirah Village Circle · Binghatti 70.01%Planned Feb 28, 2026, 8 months ago