VIVIDA Residences
VIVIDA Residences is a building project in Dubai South Residential District, Dubai, by N A M O Real Estate Development. The Dubai Land Department's register puts it at 0.84% complete, with planned completion on Sep 30, 2027.
Planned completion: Sep 30, 2027. Time left: 11 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 4168), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 0.84%, as published by the Dubai Land Department
- Planned completion
- Sep 30, 2027
- Construction start
- Feb 1, 2026
- Units
- 66
- Buildings
- 1
- Developer
- N A M O Real Estate Development
- Master developer
- Dubai Aviation City Corporation
- Community
- Dubai South Residential District, in DLD's area Madinat Al Mataar
- DLD project number
- 4168
The register describes it as: "G+4+R Residential Building"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 0.84% | Sep 30, 2027 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
3 off-plan sales in VIVIDA Residences have been registered with the Dubai Land Department, worth AED 3.5 million in all, the first on Jun 18, 2026 and the latest on Jun 24, 2026. The median price over the last 12 months was AED 13,923 per square meter (AED 1,293 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Dubai South Residential District
- Avenew888-Loom Dubai South Residential District · Avenew Real Estate Development 1.63%Planned completion Mar 31, 2028
- Windsor House Dubai South Residential District · Ellington 3.08%Planned completion Jul 31, 2029
- Windsor House II Dubai South Residential District · Ellington 0.6%Planned completion Jul 31, 2029
- Zura Residences Dubai South Residential District · Alyakka Developers 0%Planned completion Mar 31, 2029
- Avenew888 - Modo Dubai South Residential District · Avenew Real Estate Development 21.21%Planned completion Mar 15, 2028
- South Living Dubai South Residential District · Dubai South 88.83%Planned Feb 5, 2020, 6 years 9 months ago