70.16%complete

W1

W1 is a building project in Al Furjan, Dubai, by Malina W1 Real Estate Development. The Dubai Land Department's register puts it at 70.16% complete, with planned completion on Apr 30, 2026.

Planned completion was Apr 30, 2026. Time since: 6 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 4130), which also shows the latest inspection date and photos.

Facts

Status
Past planned completion
Official progress
70.16%, as published by the Dubai Land Department
Planned completion
Apr 30, 2026
Construction start
Mar 14, 2024
Units
83
Buildings
1
Developer
Malina W1 Real Estate Development
Master developer
Nakheel .(P J S C)
Community
Al Furjan, in DLD's area Jabal Ali First
Escrow bank
Abu Dhabi Islamic Bank
DLD project number
4130

The register describes it as: "Construction of G+2P+1ST+12TH+R Residential Building on plot no. AFMU020B"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202670.16%Apr 30, 2026

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.