Woodland Terraces
Woodland Terraces is a building project in Mohammed Bin Rashid Al Maktoum District 11, Dubai, by A M I S Real Estate Development. The Dubai Land Department's register puts it at 10.34% complete, with planned completion on Mar 30, 2027.
Planned completion: Mar 30, 2027. Time left: 5 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3457), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 10.34%, as published by the Dubai Land Department
- Planned completion
- Mar 30, 2027
- Construction start
- Feb 3, 2025
- Units
- 78
- Buildings
- 1
- Developer
- A M I S Real Estate Development
- Master developer
- Meydan Group
- Community
- Mohammed Bin Rashid Al Maktoum District 11, in DLD's area Wadi Al Safa 3
- Escrow bank
- United Bank Limited (management Office)
- DLD project number
- 3457
The register describes it as: "2B+G+5+Roof"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 10.34% | Mar 30, 2027 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
50 off-plan sales in Woodland Terraces have been registered with the Dubai Land Department, worth AED 77.3 million in all, the first on Feb 28, 2025 and the latest on May 11, 2026. The median price over the last 12 months was AED 19,242 per square meter (AED 1,788 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Mohammed Bin Rashid Al Maktoum District 11
- Gate Eleven Residences Mohammed Bin Rashid Al Maktoum District 11 · Amwaj 30.58%Planned completion Mar 31, 2028
- Art House Private Residences by Viva Mohammed Bin Rashid Al Maktoum District 11 · Viva Real Estate Development 0%Planned completion Feb 15, 2028
- High Best Tower Mohammed Bin Rashid Al Maktoum District 11 · True Future Real Estate Development 90.64%Planned Nov 1, 2026, 6 days ago
- Rome 3 by SD Mohammed Bin Rashid Al Maktoum District 11 · Samana 10.2%Planned completion Jun 30, 2028
- The Willows Residences Mohammed Bin Rashid Al Maktoum District 11 · Scc Vertex Property 0.74%Planned completion Jun 30, 2027
- The Cube Quarter Residences Mohammed Bin Rashid Al Maktoum District 11 · Amwaj 57.03%Planned completion Dec 31, 2026