10.34%complete

Woodland Terraces

Woodland Terraces is a building project in Mohammed Bin Rashid Al Maktoum District 11, Dubai, by A M I S Real Estate Development. The Dubai Land Department's register puts it at 10.34% complete, with planned completion on Mar 30, 2027.

Planned completion: Mar 30, 2027. Time left: 5 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3457), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
10.34%, as published by the Dubai Land Department
Planned completion
Mar 30, 2027
Construction start
Feb 3, 2025
Units
78
Buildings
1
Developer
A M I S Real Estate Development
Master developer
Meydan Group
Community
Mohammed Bin Rashid Al Maktoum District 11, in DLD's area Wadi Al Safa 3
Escrow bank
United Bank Limited (management Office)
DLD project number
3457

The register describes it as: "2B+G+5+Roof"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202610.34%Mar 30, 2027

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

50 off-plan sales in Woodland Terraces have been registered with the Dubai Land Department, worth AED 77.3 million in all, the first on Feb 28, 2025 and the latest on May 11, 2026. The median price over the last 12 months was AED 19,242 per square meter (AED 1,788 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.

More in Mohammed Bin Rashid Al Maktoum District 11

More by A M I S Real Estate Development