Al Qudra Estates off-plan projects in Dubai
Al Qudra Estates has 1 project registered with the Dubai Land Department and not yet complete, 1 past the planned completion date. Of its 1 project finished since 2024, 0 finished by the planned date in the register.
Not yet complete
| Project | Community | Units | Planned completion | Progress |
|---|---|---|---|---|
| Nad Al Sheba Gardens Phase 3 | Nad Al Sheba Gardens | 0 | Apr 19, 2026 | 97.03% |
Finished since 2024
| Project | Community | Planned | Completed |
|---|---|---|---|
| Nad Al Sheba Gardens Phase 2 | Nad Al Sheba Gardens | Dec 1, 2024 | Dec 17, 2025 |
The planned date is the one in the register at completion, which may itself have been revised.