Nad Al Sheba Gardens Phase 2
Nad Al Sheba Gardens Phase 2 is a villa project in Nad Al Sheba Gardens, Dubai, by Al Qudra Estates. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Dec 1, 2024.
Completed on Dec 17, 2025, against a planned date of Dec 1, 2024.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2390), which also shows the latest inspection date and photos.
Facts
- Status
- Completed
- Official progress
- 100%, as published by the Dubai Land Department
- Planned completion
- Dec 1, 2024
- Construction start
- Jul 10, 2022
- Villas
- 212
- Developer
- Al Qudra Estates
- Master developer
- Shamal Estates
- Community
- Nad Al Sheba Gardens, in DLD's area Nad Al Shiba First
- Escrow bank
- Commercial Bank of Dubai(psc)
- DLD project number
- 2390
The register describes it as: "Project Description: Residential - Total number of 213 Townhouses & Villas (G+1 &G+2) as follows: 48 Townhouses (G+1) ? 72 Townhouses (G+2) ? 12 Villas Semidetached (G+2) ? 4 (Villas Semidetached (G+1 ? 77 Villas Standalone (G+2)"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 100% | Dec 1, 2024 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
16 off-plan sales in Nad Al Sheba Gardens Phase 2 have been registered with the Dubai Land Department, worth AED 90.8 million in all, the first on Jul 16, 2024 and the latest on Sep 12, 2025.
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Nad Al Sheba Gardens
- Queen's Garden Nad Al Sheba Gardens · H M K Real Estate Development 42.22%Planned Aug 1, 2026, 3 months ago
- Ethan Nad Al Sheba Gardens · Griffin Real Estate Development 63.67%Planned Jun 30, 2026, 4 months ago
- One by Nine Nad Al Sheba Gardens · Nine Asset Developments 50.27%Planned Nov 8, 2025, 1 year ago
- La Vue Parc Nad Al Sheba Gardens · Maaia Prime Real Estate Developers 15.39%Planned completion Sep 15, 2027
- Nad Al Sheba Gardens Phase 3 Nad Al Sheba Gardens · Al Qudra Estates 97.03%Planned Apr 19, 2026, 7 months ago
- Nad Al Sheba Gardens Phase 4 Nad Al Sheba Gardens · Nas Estates 76.3%No planned date in the register