Alyakka Developers off-plan projects in Dubai

Alyakka Developers has 2 projects registered with the Dubai Land Department and not yet complete, 1 past the planned completion date. Of its 1 project finished since 2024, 0 finished by the planned date in the register.

Not yet complete

ProjectCommunityUnitsPlanned completionProgress
RYAH LIVING by ALYAKKADubai Studio City128Jul 30, 202654.1%
Zura ResidencesDubai South Residential District321Mar 31, 20290%

Finished since 2024

ProjectCommunityPlannedCompleted
WAHA LIVING by AL YAKKAJumeirah Garden CitySep 30, 2025Apr 7, 2026

The planned date is the one in the register at completion, which may itself have been revised.