RYAH LIVING by ALYAKKA
RYAH LIVING by ALYAKKA is a building project in Dubai Studio City, Dubai, by Alyakka Developers. The Dubai Land Department's register puts it at 54.1% complete, with planned completion on Jul 30, 2026.
Planned completion was Jul 30, 2026. Time since: 3 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 4082), which also shows the latest inspection date and photos.
Facts
- Status
- Past planned completion
- Official progress
- 54.1%, as published by the Dubai Land Department
- Planned completion
- Jul 30, 2026
- Construction start
- May 1, 2025
- Units
- 128
- Buildings
- 1
- Developer
- Alyakka Developers
- Master developer
- Dham
- Community
- Dubai Studio City, in DLD's area Al Hebiah Second
- Escrow bank
- Emirates NBD Bank
- DLD project number
- 4082
The register describes it as: "Residential Building B+G+8"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 54.1% | Jul 30, 2026 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
98 off-plan sales in RYAH LIVING by ALYAKKA have been registered with the Dubai Land Department, worth AED 93.3 million in all, the first on Feb 4, 2026 and the latest on Oct 14, 2026. 4 of them in the last 90 days. The median price over the last 12 months was AED 17,612 per square meter (AED 1,636 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Dubai Studio City
- Beach Oasis 2 Dubai Studio City · Azizi 53.22%Planned Apr 30, 2026, 6 months ago
- Arisha Terraces Dubai Studio City · Qube Development 34.04%Planned completion Oct 1, 2027
- The First Collection at Dubai Studio City Dubai Studio City · Tfg S C Development 31.86%Planned completion Jan 31, 2028
- Laya Courtyard Dubai Studio City · Laya 50.57%Planned completion Dec 26, 2026
- Verano by Prescott Dubai Studio City · Prescott 41.07%Planned completion Dec 31, 2026
- Samana Mykonos Dubai Studio City · Samana 91.12%Planned Apr 30, 2026, 6 months ago