Danube off-plan projects in Dubai

Danube has 21 projects registered with the Dubai Land Department and not yet complete, 4 past the planned completion date. Of its 5 projects finished since 2024, 4 finished by the planned date in the register.

Not yet complete

Finished since 2024

ProjectCommunityPlannedCompleted
SKYZ by DanubeArjanNov 1, 2024Nov 21, 2025
Petalz by DanubeWarsan First DevelopmentDec 31, 2025Oct 29, 2025
Opalz by DanubeDubai Science ParkApr 24, 2025Apr 24, 2025
GEMZ by DanubeAl FurjanMar 31, 2025Mar 31, 2025
PEARLZ by DanubeAl FurjanJan 31, 2025Jan 31, 2025

The planned date is the one in the register at completion, which may itself have been revised.