Danube off-plan projects in Dubai
Danube has 21 projects registered with the Dubai Land Department and not yet complete, 4 past the planned completion date. Of its 5 projects finished since 2024, 4 finished by the planned date in the register.
Not yet complete
Finished since 2024
| Project | Community | Planned | Completed |
|---|---|---|---|
| SKYZ by Danube | Arjan | Nov 1, 2024 | Nov 21, 2025 |
| Petalz by Danube | Warsan First Development | Dec 31, 2025 | Oct 29, 2025 |
| Opalz by Danube | Dubai Science Park | Apr 24, 2025 | Apr 24, 2025 |
| GEMZ by Danube | Al Furjan | Mar 31, 2025 | Mar 31, 2025 |
| PEARLZ by Danube | Al Furjan | Jan 31, 2025 | Jan 31, 2025 |
The planned date is the one in the register at completion, which may itself have been revised.