Oasiz 2 by Danube
Oasiz 2 by Danube is a building project in Silicon Oasis, Dubai, by Danube Properties Development. The Dubai Land Department's register puts it at 31% complete, with planned completion on Nov 30, 2027.
Planned completion: Nov 30, 2027. Time left: 1 year 1 month
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3260), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 31%, as published by the Dubai Land Department
- Planned completion
- Nov 30, 2027
- Construction start
- Dec 1, 2024
- Units
- 483
- Buildings
- 1
- Developer
- Danube Properties Development
- Master developer
- Dubai Integrated Economic Zones authority
- Community
- Silicon Oasis, in DLD's area Nadd Hessa
- DLD project number
- 3260
The register describes it as: "Mixed use building 1B+G+4p+32+R.The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 31% | Nov 30, 2027 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
484 off-plan sales in Oasiz 2 by Danube have been registered with the Dubai Land Department, worth AED 469 million in all, the first on Oct 30, 2024 and the latest on Oct 29, 2026. 12 of them in the last 90 days. The median price over the last 12 months was AED 21,312 per square meter (AED 1,980 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Silicon Oasis
- Timez by Danube Silicon Oasis · Danube 21.45%Planned completion Jul 31, 2028
- Tria by Deyaar Silicon Oasis · Deyaar 94.11%Planned Jun 30, 2025, 1 year 4 months ago
- Oasiz 1 by Danube Silicon Oasis · Danube 30.36%Planned completion Nov 30, 2027
- The Hillgate Silicon Oasis · Ellington 3.12%Planned completion Jun 30, 2028
- Serenova Silicon Oasis · POB1 Properties 1.55%Planned completion Mar 31, 2028
- Oasis Loft Silicon Oasis · Oasis Lofts Properties 50.08%Planned Sep 30, 2026, 38 days ago
More by Danube
- Bayz 101 by Danube Business Bay · Danube 10%No planned date in the register
- Serenz by Danube Jumeirah Village Circle · Danube 0.08%Planned completion Dec 31, 2029
- Diamondz by Danube DMCC Master Community · Danube 18.5%No planned date in the register
- Breez by Danube Dubai Maritime City · Danube 0.14%Planned completion Jun 30, 2029
- Sportz by Danube Dubai Sports City · Danube 80.22%Planned Mar 30, 2026, 7 months ago
- Bayz 102 by Danube Business Bay · Danube 6.52%Planned completion Dec 31, 2029