Ellington off-plan projects in Dubai
Ellington has 24 projects registered with the Dubai Land Department and not yet complete, 6 past the planned completion date. Of its 4 projects finished since 2024, 4 finished by the planned date in the register.
Registered under 5 company names: Ellington Properties Development, Ellington Dutco Real Estate, Ellington Karma Developers, Ellington Pcfc Developers, Ellington Sb Development.
Not yet complete
Finished since 2024
| Project | Community | Planned | Completed |
|---|---|---|---|
| Belmont Residences | Jumeirah Village Triangle | Aug 24, 2026 | |
| Hamilton House | Jumeirah Village Circle | Jan 30, 2025 | Jan 30, 2025 |
| Berkeley Place | Sobha Hartland | Dec 31, 2024 | Dec 31, 2024 |
| Belgravia Heights II | Jumeirah Village Circle | Sep 27, 2024 | Sep 27, 2024 |
| Kensington Waters | Sobha Hartland | Jun 30, 2024 | Jun 30, 2024 |
The planned date is the one in the register at completion, which may itself have been revised.