Art Bay East
Art Bay East is a building project in Jaddaf Waterfront, Dubai, by Ellington Dutco Real Estate. The Dubai Land Department's register puts it at 19.37% complete.
The register gives no planned completion date for this project.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2994), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 19.37%, as published by the Dubai Land Department
- Construction start
- Mar 12, 2024
- Units
- 103
- Buildings
- 1
- Developer
- Ellington Dutco Real Estate
- Master developer
- Culture Village
- Community
- Jaddaf Waterfront, in DLD's area Al Jadaf
- Escrow bank
- Commercial Bank of Dubai(psc)
- DLD project number
- 2994
The register describes it as: "G+10+R.The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Nov 2, 2026 | 19.37% | |
| Oct 29, 2026 | 10.42% |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
103 off-plan sales in Art Bay East have been registered with the Dubai Land Department, worth AED 224 million in all, the first on Jun 27, 2024 and the latest on Mar 11, 2026. The median price over the last 12 months was AED 24,138 per square meter (AED 2,242 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Jaddaf Waterfront
- Boutique 23 Jaddaf Waterfront · Continental Investments Lmd 64.86%No planned date in the register
- Binghatti Moonlight Jaddaf Waterfront · Binghatti 19.24%Planned Jun 15, 2026, 5 months ago
- Binghatti Twilight Jaddaf Waterfront · Binghatti 55.41%Planned Apr 30, 2026, 6 months ago
- Montage Jaddaf Waterfront · Key Mavens Montage Real Estate Development 40%Planned completion Aug 31, 2027
- Art Bay West Jaddaf Waterfront · Ellington 9.11%No planned date in the register
- Val by Kasco Jaddaf Waterfront · Kasco Real Estate Development 72.55%Planned completion Dec 30, 2026
More by Ellington
- Eltiera Views Jumeirah Islands · Ellington 0%Planned completion Dec 31, 2029
- Belgravia Gardens Falcon City · Ellington 3.08%Planned completion Sep 30, 2028
- Ellington Sands I Palm Deira · Ellington 0.37%Planned completion Dec 31, 2028
- Ellington Sands II Palm Deira · Ellington 0.38%Planned completion Dec 31, 2028
- Windsor House Dubai South Residential District · Ellington 3.08%Planned completion Jul 31, 2029
- Windsor House II Dubai South Residential District · Ellington 0.6%Planned completion Jul 31, 2029