Jumeirah Hills Development off-plan projects in Dubai
Jumeirah Hills Development has 3 projects registered with the Dubai Land Department and not yet complete. Of its 4 projects finished since 2024, 1 finished by the planned date in the register.
Not yet complete
| Project | Community | Units | Planned completion | Progress |
|---|---|---|---|---|
| Elara | Um Suqaim Third | 238 | Nov 25, 2026 | 64.27% |
| Nourelle | Um Suqaim Third | 236 | Mar 1, 2029 | 3.95% |
| Riwa | Um Suqaim Third | 244 | 12.52% |
Finished since 2024
| Project | Community | Planned | Completed |
|---|---|---|---|
| Jomana | Um Suqaim Third | Apr 30, 2026 | Sep 8, 2026 |
| Lamaa | Um Suqaim Third | Jan 27, 2026 | Jul 16, 2026 |
| Al Jazi - Madinat Jumeriah Living | Um Suqaim Third | Dec 15, 2024 | Oct 27, 2025 |
| Jadeel -Madinat Jumeirah Living | Um Suqaim Third | Sep 15, 2024 | Sep 15, 2024 |
The planned date is the one in the register at completion, which may itself have been revised.