100%complete

Jomana

Jomana is a building project in Um Suqaim Third, Dubai, by Jumeirah Hills Development. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Apr 30, 2026.

Completed on Sep 8, 2026, against a planned date of Apr 30, 2026.

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2582), which also shows the latest inspection date and photos.

Facts

Status
Completed
Official progress
100%, as published by the Dubai Land Department
Planned completion
Apr 30, 2026
Construction start
Apr 30, 2023
Units
326
Buildings
8
Developer
Jumeirah Hills Development
Community
Um Suqaim Third
Escrow bank
Emirates NBD Bank
DLD project number
2582

The register describes it as: "8 x Townhouses: G+5 Residential, The project designed to have a concrete structure and block with internal and external finishes."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 2026100%Apr 30, 2026

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

388 off-plan sales in Jomana have been registered with the Dubai Land Department, worth AED 1.48 billion in all, the first on Jun 7, 2023 and the latest on Aug 14, 2026. 1 of them in the last 90 days. The median price over the last 12 months was AED 29,638 per square meter (AED 2,753 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.