Nabni off-plan projects in Dubai
Nabni has 4 projects registered with the Dubai Land Department and not yet complete. Of its 1 project finished since 2024, 1 finished by the planned date in the register.
Registered under 2 company names: Nabni Real Estate Development, Nabni Almustaqbal Properties Development.
Not yet complete
| Project | Community | Units | Planned completion | Progress |
|---|---|---|---|---|
| Avenue Residence 7 by Nabni | Al Furjan | 166 | Oct 31, 2027 | 17.32% |
| Avenue Residence 8 | Al Furjan | 104 | Jun 30, 2028 | 17.8% |
| Nabni Sky Royal Residences | Business Bay | 146 | Dec 31, 2030 | 0% |
| Avenue Residence 6 | Al Furjan | 96 | 82.26% |
Finished since 2024
| Project | Community | Planned | Completed |
|---|---|---|---|
| Avenue Residence 5 | Al Furjan | Oct 20, 2025 | |
| Avenue Residence 4 | Al Furjan | Jan 31, 2024 | Jan 31, 2024 |
The planned date is the one in the register at completion, which may itself have been revised.