17.32%complete

Avenue Residence 7 by Nabni

Avenue Residence 7 by Nabni is a building project in Al Furjan, Dubai, by Nabni Real Estate Development. The Dubai Land Department's register puts it at 17.32% complete, with planned completion on Oct 31, 2027.

Planned completion: Oct 31, 2027. Time left: 1 year

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3300), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
17.32%, as published by the Dubai Land Department
Planned completion
Oct 31, 2027
Construction start
Sep 17, 2024
Units
166
Buildings
1
Developer
Nabni Real Estate Development
Master developer
Alfurjan ( L.L.C )
Community
Al Furjan, in DLD's area Jabal Ali First
DLD project number
3300

The register describes it as: "Ground+Parking+10 Floor + Roof Residential Building"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202617.32%Oct 31, 2027

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

126 off-plan sales in Avenue Residence 7 by Nabni have been registered with the Dubai Land Department, worth AED 260 million in all, the first on Nov 20, 2024 and the latest on Oct 8, 2026. 2 of them in the last 90 days. The median price over the last 12 months was AED 16,081 per square meter (AED 1,494 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.