Tabeer Real Estate Development off-plan projects in Dubai
Tabeer Real Estate Development has 3 projects registered with the Dubai Land Department and not yet complete, 1 past the planned completion date. Of its 1 project finished since 2024, 0 finished by the planned date in the register.
Not yet complete
| Project | Community | Units | Planned completion | Progress |
|---|---|---|---|---|
| 99 Park Place | Jumeirah Village Circle | 102 | Dec 31, 2025 | 90% |
| Parkside Boulevard | Arjan | 171 | Dec 27, 2027 | 51.93% |
| 368 Park Ln | Jumeirah Village Circle | 213 | Aug 31, 2028 | 0% |
Finished since 2024
| Project | Community | Planned | Completed |
|---|---|---|---|
| 48 Parkside | Arjan | Sep 30, 2025 | May 11, 2026 |
The planned date is the one in the register at completion, which may itself have been revised.