Parkside Boulevard
Parkside Boulevard is a building project in Arjan, Dubai, by Tabeer Real Estate Development. The Dubai Land Department's register puts it at 51.93% complete, with planned completion on Dec 27, 2027.
Planned completion: Dec 27, 2027. Time left: 1 year 2 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3326), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 51.93%, as published by the Dubai Land Department
- Planned completion
- Dec 27, 2027
- Construction start
- Nov 14, 2024
- Units
- 171
- Buildings
- 1
- Developer
- Tabeer Real Estate Development
- Master developer
- Liwan
- Community
- Arjan, in DLD's area Al Barshaa South Third
- Escrow bank
- First Abu Dhabi Bank
- DLD project number
- 3326
The register describes it as: "B + G + 9 + GYM + Pool on the roof.The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 51.93% | Dec 27, 2027 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
128 off-plan sales in Parkside Boulevard have been registered with the Dubai Land Department, worth AED 134 million in all, the first on Feb 10, 2025 and the latest on Oct 27, 2026. 4 of them in the last 90 days. The median price over the last 12 months was AED 15,264 per square meter (AED 1,418 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Arjan
- The central downtown Arjan · Aqua 10.48%Planned completion Mar 31, 2028
- Vincitore Dolce Vita Arjan · Vincitore 40%No planned date in the register
- Kyoto by ORO24 Arjan · ORO24 Real Estate Development 16.96%Planned Sep 20, 2026, 2 months ago
- Ashley Hills Arjan · Townx Real Estate Development 74.05%Planned completion Mar 31, 2027
- Butterfly Arjan · Desert Falcon Real Estate Development 7.65%Planned completion Jan 31, 2029
- Marquis One Arjan · Marquis Home Developer 0.29%Planned completion Dec 31, 2028