Taraf off-plan projects in Dubai
Taraf has 5 projects registered with the Dubai Land Department and not yet complete, 1 past the planned completion date. Of its 1 project finished since 2024, 0 finished by the planned date in the register.
Registered under 2 company names: Taraf Development, Taraf Properties.
Not yet complete
| Project | Community | Units | Planned completion | Progress |
|---|---|---|---|---|
| Terrazzo Residences | Jumeirah Village Circle | 211 | May 20, 2026 | 95.2% |
| Terra Golf Collection | Jumeirah Golf Estates | 0 | Dec 31, 2027 | 20.05% |
| Taraf 3 Residence | Jumeirah Village Circle | 151 | Mar 31, 2028 | 6.94% |
| Cello Residences | Jumeirah Village Circle | 392 | 38.98% | |
| Karl Lagerfeld Villas by Taraf | Mohammed Bin Rashid Al Maktoum District 11 | 0 | 10.51% |
Finished since 2024
| Project | Community | Planned | Completed |
|---|---|---|---|
| Luce | Palm Jumeirah | Dec 31, 2025 | Oct 20, 2026 |
The planned date is the one in the register at completion, which may itself have been revised.