10.51%complete

Karl Lagerfeld Villas by Taraf

Karl Lagerfeld Villas by Taraf is a villa community in Mohammed Bin Rashid Al Maktoum District 11, Dubai, by Taraf Development. The Dubai Land Department's register puts it at 10.51% complete.

The register gives no planned completion date for this project.

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2982), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
10.51%, as published by the Dubai Land Department
Construction start
Sep 1, 2024
Villas
51
Developer
Taraf Development
Master developer
Meydan Group
Community
Mohammed Bin Rashid Al Maktoum District 11, in DLD's area Wadi Al Safa 3
Escrow bank
First Abu Dhabi Bank
DLD project number
2982

The register describes it as: "51 nos (G + 2)residential villas and 2 amenities. Villas. The project designed to have a concrete structure and block with internal and external finishes."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202610.51%

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

35 off-plan sales in Karl Lagerfeld Villas by Taraf have been registered with the Dubai Land Department, worth AED 933 million in all, the first on Jul 9, 2024 and the latest on Aug 10, 2026. 1 of them in the last 90 days. The median price over the last 12 months was AED 32,619 per square meter (AED 3,030 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.