Tarrad off-plan projects in Dubai
Tarrad has 3 projects registered with the Dubai Land Department and not yet complete, 1 past the planned completion date.
Not yet complete
| Project | Community | Units | Planned completion | Progress |
|---|---|---|---|---|
| Mackerel Tower | Palm Deira | 62 | Apr 1, 2026 | 56.58% |
| Celesto Tower | Dubai Land Residence Complex | 271 | Dec 31, 2027 | 3.89% |
| Celesto Tower 2 | Dubai Land Residence Complex | 231 | Jun 28, 2028 | 0% |