Mackerel Tower
Mackerel Tower is a building project in Palm Deira, Dubai, by Tarrad Development. The Dubai Land Department's register puts it at 56.58% complete, with planned completion on Apr 1, 2026.
Planned completion was Apr 1, 2026. Time since: 7 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3351), which also shows the latest inspection date and photos.
Facts
- Status
- Past planned completion
- Official progress
- 56.58%, as published by the Dubai Land Department
- Planned completion
- Apr 1, 2026
- Construction start
- Nov 1, 2024
- Units
- 62
- Buildings
- 1
- Developer
- Tarrad Development
- Master developer
- The Palm - Deira
- Community
- Palm Deira
- Escrow bank
- First Abu Dhabi Bank
- DLD project number
- 3351
The register describes it as: "Residential Building (G+P+8+R).The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Nov 2, 2026 | 56.58% | Apr 1, 2026 |
| Oct 29, 2026 | 45.58% | Apr 1, 2026 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
44 off-plan sales in Mackerel Tower have been registered with the Dubai Land Department, worth AED 92.1 million in all, the first on Dec 17, 2024 and the latest on Oct 5, 2026. 2 of them in the last 90 days. The median price over the last 12 months was AED 19,406 per square meter (AED 1,803 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Palm Deira
- The Meriva Collection Palm Deira · Crestarc Developers 0.1%Planned completion Dec 31, 2031
- Hado by Beyond Palm Deira · Sandy Shores Real Estate L.L.C S.o.c 0.01%Planned completion Jun 30, 2029
- Ellington Sands I Palm Deira · Ellington 0.37%Planned completion Dec 31, 2028
- Ellington Sands II Palm Deira · Ellington 0.38%Planned completion Dec 31, 2028
- Bay Grove Residences C - Dubai Islands Palm Deira · Dubai Islands 7.29%Planned completion Apr 10, 2028
- Beach Residences Dubai Islands Palm Deira · Nakheel 28.8%No planned date in the register