0.02%complete

241 Waterside

241 Waterside is a building project in Palm Deira, Dubai, by Legacy Star Real Estate Development. The Dubai Land Department's register puts it at 0.02% complete (not started), with planned completion on Jun 15, 2028.

Planned completion: Jun 15, 2028. Time left: 1 year 7 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 4093), which also shows the latest inspection date and photos.

Facts

Status
Not started
Official progress
0.02%, as published by the Dubai Land Department
Planned completion
Jun 15, 2028
Construction start
Jan 15, 2026
Units
63
Buildings
1
Developer
Legacy Star Real Estate Development
Master developer
The Palm - Deira
Community
Palm Deira
Escrow bank
Emirates NBD Bank
DLD project number
4093

The register describes it as: "Residential Building(G+2P+8 Floors Roof) + Entertainment area @ Podium 2F + Swimming Pool @ Roof"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 20260.02%Jun 15, 2028

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

16 off-plan sales in 241 Waterside have been registered with the Dubai Land Department, worth AED 37.5 million in all, the first on Feb 25, 2026 and the latest on Jul 2, 2026. The median price over the last 12 months was AED 21,414 per square meter (AED 1,989 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.