Al Habtoor Tower
Al Habtoor Tower is a building project in Business Bay, Dubai, by Al Habtoor City Real Estate Development (br. of Dubai National Investment Co. The Dubai Land Department's register puts it at 90.01% complete, with planned completion on Dec 31, 2026.
Planned completion: Dec 31, 2026. Time left: 2 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2656), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 90.01%, as published by the Dubai Land Department
- Planned completion
- Dec 31, 2026
- Construction start
- Oct 1, 2022
- Units
- 1,739
- Buildings
- 1
- Developer
- Al Habtoor City Real Estate Development (br. of Dubai National Investment Co
- Master developer
- Business Bay
- Community
- Business Bay
- Escrow bank
- Dubai Islamic Bank
- DLD project number
- 2656
The register describes it as: "High Rise Residential Building 82 floors on Sh. Zayed Road(As per BP:- 3B+G+7P+77F, Residential/commercial).The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 90.01% | Dec 31, 2026 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
1,309 off-plan sales in Al Habtoor Tower have been registered with the Dubai Land Department, worth AED 4.41 billion in all, the first on Aug 22, 2023 and the latest on Nov 5, 2026. 13 of them in the last 90 days. The median price over the last 12 months was AED 29,841 per square meter (AED 2,772 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Business Bay
- Binghatti Skyrise Business Bay · Binghatti 35.89%Planned completion Dec 31, 2026
- Binghatti Aquarise Business Bay · Binghatti 21.04%Planned Oct 31, 2026, 7 days ago
- Bayz 101 by Danube Business Bay · Danube 10%No planned date in the register
- Aykon City 3 Business Bay · Damac 31.35%Planned completion Dec 30, 2027
- Bayz 102 by Danube Business Bay · Danube 6.52%Planned completion Dec 31, 2029
- Tiger Sky Tower Business Bay · Tiger 10.24%No planned date in the register