Binghatti Skyrise is a building project in Business Bay, Dubai, by Binghatti Developers. The Dubai Land Department's register puts it at 35.89% complete, with planned completion on Dec 31, 2026.
Planned completion: Dec 31, 2026. Time left: 2 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3349), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 35.89%, as published by the Dubai Land Department
- Planned completion
- Dec 31, 2026
- Construction start
- Oct 15, 2024
- Units
- 3,358
- Buildings
- 4
- Developer
- Binghatti Developers
- Master developer
- Business Bay
- Community
- Business Bay
- Escrow bank
- Dubai Islamic Bank
- DLD project number
- 3349
The register describes it as: "5B + G + 4P + 49 RESIDENTIAL FLOORS + 2MECH + ROOF ( 3 TOWERS)"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 35.89% | Dec 31, 2026 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
3,318 off-plan sales in Binghatti Skyrise have been registered with the Dubai Land Department, worth AED 5.38 billion in all, the first on Dec 20, 2024 and the latest on Nov 3, 2026. 19 of them in the last 90 days. The median price over the last 12 months was AED 32,717 per square meter (AED 3,040 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Business Bay
- Al Habtoor Tower Business Bay · Al Habtoor 90.01%Planned completion Dec 31, 2026
- Binghatti Aquarise Business Bay · Binghatti 21.04%Planned Oct 31, 2026, 7 days ago
- Bayz 101 by Danube Business Bay · Danube 10%No planned date in the register
- Aykon City 3 Business Bay · Damac 31.35%Planned completion Dec 30, 2027
- Bayz 102 by Danube Business Bay · Danube 6.52%Planned completion Dec 31, 2029
- Tiger Sky Tower Business Bay · Tiger 10.24%No planned date in the register
More by Binghatti
- Binghatti Skyterraces Motor City · Binghatti 0%Planned completion Oct 31, 2027
- Maybach Six Meydan Racecourse Community · Binghatti 0%Planned completion Aug 31, 2027
- Binghatti Elite International Media Production Zone · Binghatti 53.25%Planned Jun 30, 2026, 4 months ago
- Binghatti Hills Dubai Science Park · Binghatti 90%No planned date in the register
- Binghatti Hillviews Dubai Science Park · Binghatti 32.6%Planned Apr 1, 2026, 7 months ago
- Binghatti Vintage Majan · Binghatti 0%Planned completion Mar 31, 2027