Amethyst by Siroya is a building project in Majan, Dubai, by Siroya Ventures Realty. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Nov 30, 2025.
Completed on Jul 15, 2026, against a planned date of Nov 30, 2025.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3244), which also shows the latest inspection date and photos.
Facts
- Status
- Completed
- Official progress
- 100%, as published by the Dubai Land Department
- Planned completion
- Nov 30, 2025
- Construction start
- Aug 1, 2024
- Units
- 53
- Buildings
- 1
- Developer
- Siroya Ventures Realty
- Master developer
- Liwan
- Community
- Majan, in DLD's area Wadi Al Safa 3
- Escrow bank
- Bank of Baroda
- DLD project number
- 3244
The register describes it as: "G+4+R Residential Building.The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 100% | Nov 30, 2025 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
52 off-plan sales in Amethyst by Siroya have been registered with the Dubai Land Department, worth AED 66.5 million in all, the first on Mar 25, 2025 and the latest on Jun 22, 2026. The median price over the last 12 months was AED 12,088 per square meter (AED 1,123 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Majan
- Binghatti Vintage Majan · Binghatti 0%Planned completion Mar 31, 2027
- Vincitore Wellness Estate Majan · Vincitore 0%Planned completion Feb 15, 2030
- Binghatti Skyflame 1 Majan · Binghatti 0%Planned completion Dec 31, 2027
- Binghatti Skyflame 2 Majan · Binghatti 0%Planned completion Dec 31, 2027
- Binghatti Titania Majan · Binghatti 0%Planned completion Feb 28, 2027
- Samana Barari Heights Majan · Samana 4.04%Planned completion Oct 31, 2028