Off-plan projects in Majan

32 projects in Majan are registered and not yet complete, 4 of them past the planned completion date, according to the Dubai Land Department.

Not yet complete

ProjectDeveloperUnitsPlanned completionProgress
Tulip Oasis 11A M E Real Estate Development108Jun 30, 202693.01%
Sherena Residence 2Rose Homes Investment120Aug 31, 202282.03%
Forest City TowerAl Helal Al Zahaby Real Estate Development253Apr 9, 202770.08%
The Haven IIMeraki Real Estate Development225Dec 31, 202656.29%
Wadi 645Greenside Development7055.15%
Estrella by NexusNexus Capital Real Estate Developement60May 31, 202645.5%
Barari Parkview by Al MawaredAlmawared Properties199Dec 20, 202744.7%
Mangrove 2Mangrove Real Estate Development18Sep 23, 202637.75%
Lazord by LapisLapis Properties313Dec 31, 202627.64%
Samana Barari ViewsSamana669Mar 31, 202726.81%
Divine Al BarariTakmeel Real Estate Development291Mar 31, 202820.32%
Samana Barari Views 2Samana66919.65%
Samana Barari LagoonsSamana601Mar 31, 202816.52%
Samana Business ParkSamana103Sep 30, 202812.83%
Jade TowerTiger436Mar 31, 202711%
Forum 2K X G Real Estate Development77Dec 15, 20277.03%
The Haven IIIMeraki Real Estate Development83Dec 31, 20276.17%
Samana Barari AvenueSamana349Oct 31, 20286.01%
Rabdan GatesRabdan445Jun 30, 20285.18%
Samana Barari HeightsSamana737Oct 31, 20284.04%
Rijas SuitesDusit Rijas Properties153Dec 31, 20283.33%
Samana Business Park 2Samana174Oct 31, 20282.96%
BARARIGATE by ADEA D E Properties282Dec 31, 20281.67%
Barari Parks by BahatBahat Real Estate Development52Mar 31, 20280.9%
Barari PalaceAry & Maz Development225Dec 30, 20280.04%
Blossom 40Tranquil Infra Developers66Mar 31, 20280.04%
Symphony by ChaimaaDeval Real Estate Development71Aug 31, 20270%
Binghatti VintageBinghatti1,572Mar 31, 20270%
Binghatti TitaniaBinghatti789Feb 28, 20270%
Vincitore Wellness EstateVincitore1,475Feb 15, 20300%
Binghatti Skyflame 1Binghatti1,407Dec 31, 20270%
Binghatti Skyflame 2Binghatti801Dec 31, 20270%