Arabian Ranches lll - Elie Saab ll
Arabian Ranches lll - Elie Saab ll is a villa project in Arabian Ranches 3, Dubai, by Emaar Development. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Nov 30, 2025.
Completed on Sep 15, 2025, against a planned date of Nov 30, 2025.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2346), which also shows the latest inspection date and photos.
Facts
- Status
- Completed
- Official progress
- 100%, as published by the Dubai Land Department
- Planned completion
- Nov 30, 2025
- Construction start
- Apr 27, 2022
- Developer
- Emaar Development
- Community
- Arabian Ranches 3, in DLD's area Wadi Al Safa 5
- Escrow bank
- Commercial Bank of Dubai(psc)
- DLD project number
- 2346
The register describes it as: "131 (G+2) mix of: 4 bed and 5 bed types of Villas, The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 100% | Nov 30, 2025 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
More by Emaar
- The St. Regis Residences, Downtown Dubai DownTown Dubai · Emaar 76.05%Planned completion Dec 25, 2026
- Palace by the Beach Dubai Harbour · Emaar 0%Planned completion Nov 30, 2031
- Avarra by Palace Business Bay · Emaar 0.08%Planned completion Jun 30, 2031
- Bayview Dubai Harbour · Emaar 63.02%Planned completion Jul 31, 2028
- Seapoint Dubai Harbour · Emaar 36.78%Planned completion Mar 31, 2028
- Golf Point Dubai World Central · Emaar 4.78%Planned completion Oct 31, 2028