The St. Regis Residences, Downtown Dubai
The St. Regis Residences, Downtown Dubai is a building project in DownTown Dubai, Dubai, by Emaar Development. The Dubai Land Department's register puts it at 76.05% complete, with planned completion on Dec 25, 2026.
Planned completion: Dec 25, 2026. Time left: 2 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 1816), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 76.05%, as published by the Dubai Land Department
- Planned completion
- Dec 25, 2026
- Construction start
- Feb 28, 2017
- Units
- 1,108
- Buildings
- 3
- Developer
- Emaar Development
- Master developer
- Emaar Properties
- Community
- DownTown Dubai, in DLD's area Burj Khalifa
- Escrow bank
- Dubai Islamic Bank
- DLD project number
- 1816
The register describes it as: "Common 5B+G+2P-Tower.1:65+R & Tower. 2:44+Roof. Residential + Retail. The project is designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 76.05% | Dec 25, 2026 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
1,580 off-plan sales in The St. Regis Residences, Downtown Dubai have been registered with the Dubai Land Department, worth AED 5.96 billion in all, the first on Feb 23, 2022 and the latest on Nov 5, 2026. 25 of them in the last 90 days. The median price over the last 12 months was AED 33,545 per square meter (AED 3,116 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in DownTown Dubai
- Binghatti Skyblade DownTown Dubai · Binghatti 17.06%Planned completion Nov 30, 2027
- One Residence DownTown Dubai · Ginco Properties 6.33%Planned completion Mar 31, 2027
- City Center Residences DownTown Dubai · Dar Global Properties 72.3%Planned Sep 30, 2026, 38 days ago
- ROVE HOME RESIDENCES by IRTH DownTown Dubai · Irth Development 62.69%Planned Apr 30, 2026, 6 months ago
- Euphoric Residences DownTown Dubai · East & West Properties 8.3%Planned completion Dec 31, 2027
- Solara Tower Dubai DownTown Dubai · S O L Properties Development 20.73%Planned completion Aug 15, 2027
More by Emaar
- Palace by the Beach Dubai Harbour · Emaar 0%Planned completion Nov 30, 2031
- Avarra by Palace Business Bay · Emaar 0.08%Planned completion Jun 30, 2031
- Bayview Dubai Harbour · Emaar 63.02%Planned completion Jul 31, 2028
- Seapoint Dubai Harbour · Emaar 36.78%Planned completion Mar 31, 2028
- Golf Point Dubai World Central · Emaar 4.78%Planned completion Oct 31, 2028
- Maysan Al Yelayiss 2 · Emaar 36.7%Planned Jul 1, 2016, 10 years 4 months ago