Aras Heights
Aras Heights is a building project in Majan, Dubai, by A R A S Real Estate Development. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Dec 31, 2023.
Completed on Mar 12, 2026, against a planned date of Dec 31, 2023.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2652), which also shows the latest inspection date and photos.
Facts
- Status
- Completed
- Official progress
- 100%, as published by the Dubai Land Department
- Planned completion
- Dec 31, 2023
- Construction start
- Apr 5, 2022
- Units
- 73
- Buildings
- 1
- Developer
- A R A S Real Estate Development
- Master developer
- Liwan
- Community
- Majan, in DLD's area Wadi Al Safa 3
- Escrow bank
- Arab Bank For Investment & Foreign Trade Almasref
- DLD project number
- 2652
The register describes it as: "2B+G+9Floor+R Residential, The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 100% | Dec 31, 2023 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
74 off-plan sales in Aras Heights have been registered with the Dubai Land Department, worth AED 79.9 million in all, the first on Jan 5, 2024 and the latest on Apr 6, 2026. The median price over the last 12 months was AED 11,981 per square meter (AED 1,113 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Majan
- Binghatti Vintage Majan · Binghatti 0%Planned completion Mar 31, 2027
- Vincitore Wellness Estate Majan · Vincitore 0%Planned completion Feb 15, 2030
- Binghatti Skyflame 1 Majan · Binghatti 0%Planned completion Dec 31, 2027
- Binghatti Skyflame 2 Majan · Binghatti 0%Planned completion Dec 31, 2027
- Binghatti Titania Majan · Binghatti 0%Planned completion Feb 28, 2027
- Samana Barari Heights Majan · Samana 4.04%Planned completion Oct 31, 2028