0%complete

Arib Collection

Arib Collection is a building project in Dubai Land Residence Complex, Dubai, by Arib Properties For Real Estate Development. The Dubai Land Department's register puts it at 0% complete (not started), with planned completion on Dec 1, 2027.

Planned completion: Dec 1, 2027. Time left: 1 year 1 month

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3815), which also shows the latest inspection date and photos.

Facts

Status
Not started
Official progress
0%, as published by the Dubai Land Department
Planned completion
Dec 1, 2027
Construction start
Oct 1, 2025
Units
49
Buildings
1
Developer
Arib Properties For Real Estate Development
Master developer
Dubai Land Residences
Community
Dubai Land Residence Complex, in DLD's area Wadi Al Safa 5
Escrow bank
Commercial Bank of Dubai(psc)
DLD project number
3815

The register describes it as: "G+8+R Residential Building"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 20260%Dec 1, 2027

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

2 off-plan sales in Arib Collection have been registered with the Dubai Land Department, worth AED 3 million in all, the first on Dec 11, 2025 and the latest on Jul 9, 2026. The median price over the last 12 months was AED 16,393 per square meter (AED 1,523 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.