Ascot Residences
Ascot Residences is a building project in Town Square, Dubai, by Nshama Properties. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Nov 1, 2024.
Completed on Nov 1, 2024, against a planned date of Nov 1, 2024.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2523), which also shows the latest inspection date and photos.
Facts
- Status
- Completed
- Official progress
- 100%, as published by the Dubai Land Department
- Planned completion
- Nov 1, 2024
- Construction start
- Feb 1, 2023
- Units
- 153
- Buildings
- 1
- Developer
- Nshama Properties
- Community
- Town Square, in DLD's area Al Yelayiss 2
- Escrow bank
- First Abu Dhabi Bank
- DLD project number
- 2523
The register describes it as: "G+5+R Residential & Retail, The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 100% | Nov 1, 2024 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
147 off-plan sales in Ascot Residences have been registered with the Dubai Land Department, worth AED 124 million in all, the first on Feb 21, 2023 and the latest on Dec 13, 2024.
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Town Square
- Symphony Town Square · Nshama 73.16%No planned date in the register
- Grove Town Square · Nshama 40.69%No planned date in the register
- Belmont Town Square · Nshama 0%Planned completion Apr 30, 2029
- Evelyn on the Park Town Square · Nshama 0.02%Planned completion Feb 28, 2029
- Rosewell Town Square · Nshama 0.02%Planned completion Dec 31, 2028
- Lana on the Park Town Square · Nshama 35.93%No planned date in the register
More by Nshama
- Haya on the Park Town Square · Nshama 35.33%Planned completion Feb 26, 2027
- Fia Town Square · Nshama 84.55%No planned date in the register
- Odessa Town Square · Nshama 8.01%Planned completion Dec 30, 2027
- Hillcrest Town Square · Nshama 38.36%Planned completion Jun 30, 2027
- Camden Town Square · Nshama 7.24%Planned completion Mar 31, 2028
- The Baltimore Town Square · Nshama 26.33%Planned completion Sep 30, 2027