24.46%complete

Avenue 353

Avenue 353 is a building project in City of Arabia, Dubai, by Ilyas & Mustafa Galadari Real Estate Co. The Dubai Land Department's register puts it at 24.46% complete (pending), with planned completion on Dec 31, 2025.

Planned completion was Dec 31, 2025. Time since: 10 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 1604), which also shows the latest inspection date and photos.

Facts

Status
Past planned completion
Official progress
24.46%, as published by the Dubai Land Department
Planned completion
Dec 31, 2025
Construction start
Apr 1, 2014
Villas
79
Developer
Ilyas & Mustafa Galadari Real Estate Co
Community
City of Arabia, in DLD's area Wadi Al Safa 4
Escrow bank
Commercial Bank International
DLD project number
1604

The register describes it as: "Villa community development in area Wadi Al Safa 4 - Dubai, plot # 646-5288, Proposed development consist of total 269 villas (B+G+1+R),there are 4 types of villas: Type A x 142 villas, Type B x 100 villas, Type C x 19 villas and Type D x 8 villas, development divided into two phases: phase 1 x 132 villas and phase 2 x 137 villas. Proposed construction consist of concrete structure with internal and external finishes and infrastructure works."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202624.46%Dec 31, 2025

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

46 off-plan sales in Avenue 353 have been registered with the Dubai Land Department, worth AED 226 million in all, the first on Dec 22, 2015 and the latest on Aug 7, 2018.

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.