Off-plan projects in City of Arabia
11 projects in City of Arabia are registered and not yet complete, 1 of them past the planned completion date, according to the Dubai Land Department.
Not yet complete
| Project | Developer | Units | Planned completion | Progress |
|---|---|---|---|---|
| Avenue 353 | Ilyas & Mustafa Galadari Real Estate Co | 0 | Dec 31, 2025 | 24.46% |
| Laguna Residence | One International Real Estate Development | 1,628 | Dec 31, 2027 | 5.72% |
| Azizi Milan 51 | Azizi | 579 | Mar 26, 2027 | 0% |
| Azizi Milan 30 | Azizi | 780 | Apr 4, 2027 | 0% |
| Azizi Milan 20 | Azizi | 741 | Apr 30, 2027 | 0% |
| Azizi Milan 18 | Azizi | 1,541 | Apr 16, 2027 | 0% |
| Azizi Milan 53 | Azizi | 306 | Apr 30, 2027 | 0% |
| Azizi Milan 55 | Azizi | 465 | Apr 30, 2027 | 0% |
| Azizi Milan 28 | Azizi | 610 | Jun 3, 2027 | 0% |
| Azizi Milan Heights | Azizi | 2,852 | Sep 8, 2028 | 0% |
| Arancia Yards by Beyond | Peninsula Elit Real Estate Development L.L.C S.o.c | 284 | Oct 30, 2028 | 0% |