45.87%complete

Azizi Venice 13

Azizi Venice 13 is a building project in Dubai World Central, Dubai, by Azizi Developments. The Dubai Land Department's register puts it at 45.87% complete, with planned completion on Sep 16, 2027.

Planned completion: Sep 16, 2027. Time left: 10 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3297), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
45.87%, as published by the Dubai Land Department
Planned completion
Sep 16, 2027
Construction start
Sep 16, 2024
Units
1,888
Buildings
2
Developer
Azizi Developments
Master developer
Dubai Aviation City Corporation
Community
Dubai World Central, in DLD's area Madinat Al Mataar
Escrow bank
Abu Dhabi Commercial Bank
DLD project number
3297

The register describes it as: "Tower A: 4B +G + 19 + R + TOP ROOF ? Residential & Commercial Tower B: 4B +G + 19 + R + TOP ROOF ? Residential & Commercial"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202645.87%Sep 16, 2027

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

793 off-plan sales in Azizi Venice 13 have been registered with the Dubai Land Department, worth AED 663 million in all, the first on Oct 14, 2024 and the latest on Nov 4, 2026. 86 of them in the last 90 days. The median price over the last 12 months was AED 18,004 per square meter (AED 1,673 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.