Binghatti Hillside is a building project in Dubai Science Park, Dubai, by Binghatti Developers. The Dubai Land Department's register puts it at 80% complete, with planned completion on Jun 30, 2026.
Planned completion was Jun 30, 2026. Time since: 4 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3481), which also shows the latest inspection date and photos.
Facts
- Status
- Past planned completion
- Official progress
- 80%, as published by the Dubai Land Department
- Planned completion
- Jun 30, 2026
- Construction start
- Jan 31, 2025
- Units
- 411
- Buildings
- 1
- Developer
- Binghatti Developers
- Master developer
- Dham
- Community
- Dubai Science Park, in DLD's area Al Barshaa South Second
- Escrow bank
- Dubai Islamic Bank
- DLD project number
- 3481
The register describes it as: "3B + G + 2P +21 RESIDENTIAL FLOORS + ROOF"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 80% | Jun 30, 2026 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
359 off-plan sales in Binghatti Hillside have been registered with the Dubai Land Department, worth AED 336 million in all, the first on Sep 19, 2025 and the latest on Nov 4, 2026. 85 of them in the last 90 days. The median price over the last 12 months was AED 23,164 per square meter (AED 2,152 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Dubai Science Park
- Skyhills Astra by HRE Dubai Science Park · HRE Real Estate Development 47.07%Planned completion Jun 30, 2028
- Binghatti Hills Dubai Science Park · Binghatti 90%No planned date in the register
- Binghatti Hillviews Dubai Science Park · Binghatti 32.6%Planned Apr 1, 2026, 7 months ago
- Vincitore Aqua Dimore Dubai Science Park · Vincitore 14.07%No planned date in the register
- SAAS Hills Dubai Science Park · Saas Properties L.L.C - Dubai Branch 12.98%Planned completion Mar 31, 2027
- 11 Hills Park Dubai Science Park · Townx Real Estate Development 80.05%Planned completion Mar 31, 2027
More by Binghatti
- Binghatti Skyrise Business Bay · Binghatti 35.89%Planned completion Dec 31, 2026
- Binghatti Skyterraces Motor City · Binghatti 0%Planned completion Oct 31, 2027
- Maybach Six Meydan Racecourse Community · Binghatti 0%Planned completion Aug 31, 2027
- Binghatti Elite International Media Production Zone · Binghatti 53.25%Planned Jun 30, 2026, 4 months ago
- Binghatti Aquarise Business Bay · Binghatti 21.04%Planned Oct 31, 2026, 7 days ago
- Binghatti Vintage Majan · Binghatti 0%Planned completion Mar 31, 2027