Binghatti Pinnacle
Binghatti Pinnacle is a building project in Dubai Health Care City Phase 2, Dubai, by Binghatti Developers. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Dec 31, 2025.
Completed on Jul 30, 2026, against a planned date of Dec 31, 2025.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3256), which also shows the latest inspection date and photos.
Facts
- Status
- Completed
- Official progress
- 100%, as published by the Dubai Land Department
- Planned completion
- Dec 31, 2025
- Construction start
- Sep 1, 2024
- Units
- 178
- Buildings
- 1
- Developer
- Binghatti Developers
- Master developer
- Dubai Healthcare City FZ
- Community
- Dubai Health Care City Phase 2, in DLD's area Al Jadaf
- Escrow bank
- Emirates NBD Bank
- DLD project number
- 3256
The register describes it as: "4B + G + 17 FLOORS + ROOF.The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 100% | Dec 31, 2025 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
146 off-plan sales in Binghatti Pinnacle have been registered with the Dubai Land Department, worth AED 338 million in all, the first on Oct 6, 2025 and the latest on Jul 27, 2026. The median price over the last 12 months was AED 23,139 per square meter (AED 2,150 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Dubai Health Care City Phase 2
More by Binghatti
- Binghatti Skyrise Business Bay · Binghatti 35.89%Planned completion Dec 31, 2026
- Binghatti Skyterraces Motor City · Binghatti 0%Planned completion Oct 31, 2027
- Maybach Six Meydan Racecourse Community · Binghatti 0%Planned completion Aug 31, 2027
- Binghatti Elite International Media Production Zone · Binghatti 53.25%Planned Jun 30, 2026, 4 months ago
- Binghatti Hills Dubai Science Park · Binghatti 90%No planned date in the register
- Binghatti Aquarise Business Bay · Binghatti 21.04%Planned Oct 31, 2026, 7 days ago