Bliss Tower
Bliss Tower is a building project in Dubai Land Residence Complex, Dubai, by Pure Bliss Development. The Dubai Land Department's register puts it at 92.52% complete, with planned completion on Dec 15, 2026.
Planned completion: Dec 15, 2026. Time left: 38 days
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3545), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 92.52%, as published by the Dubai Land Department
- Planned completion
- Dec 15, 2026
- Construction start
- Aug 15, 2024
- Units
- 131
- Buildings
- 1
- Developer
- Pure Bliss Development
- Master developer
- Dubai Land Residences
- Community
- Dubai Land Residence Complex, in DLD's area Wadi Al Safa 5
- DLD project number
- 3545
The register describes it as: "G+2P+12F+R.The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 92.52% | Dec 15, 2026 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
116 off-plan sales in Bliss Tower have been registered with the Dubai Land Department, worth AED 137 million in all, the first on Nov 12, 2025 and the latest on Oct 16, 2026. 1 of them in the last 90 days. The median price over the last 12 months was AED 13,350 per square meter (AED 1,240 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Dubai Land Residence Complex
- Peace Lagoons by Peace Homes Dubai Land Residence Complex · Peace Homes 4.16%Planned completion Sep 30, 2028
- Samana IVY Gardens 2 Dubai Land Residence Complex · Samana 20.03%Planned completion Dec 31, 2027
- Peace Lagoons II by Peace Homes Dubai Land Residence Complex · Peace Homes 4.04%Planned completion Jan 1, 2029
- Cove Living Residence by Imtiaz Dubai Land Residence Complex · Imtiaz 47.21%Planned completion Apr 15, 2027
- Sky Line by Peace Homes Dubai Land Residence Complex · Peace Homes 0%Planned completion May 30, 2030
- Samana Boulevard Heights Dubai Land Residence Complex · Samana 2.5%Planned completion Dec 31, 2028