City Walk Northline 1
City Walk Northline 1 is a building project in City Walk, Dubai, by Citywalk Residential 1. The Dubai Land Department's register puts it at 38.09% complete.
The register gives no planned completion date for this project.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2970), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 38.09%, as published by the Dubai Land Department
- Construction start
- Aug 10, 2024
- Units
- 115
- Buildings
- 1
- Developer
- Citywalk Residential 1
- Master developer
- Meraas Estates
- Community
- City Walk, in DLD's area Al Wasl
- Escrow bank
- First Abu Dhabi Bank
- DLD project number
- 2970
The register describes it as: "Residential Building: B + G + 8 floors + Roof consists of 1, 2, & 3 bedroom Apartments Total residential units: 114 Total retail units: 1"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 38.09% |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
121 off-plan sales in City Walk Northline 1 have been registered with the Dubai Land Department, worth AED 389 million in all, the first on Apr 4, 2024 and the latest on Oct 2, 2026. 1 of them in the last 90 days. The median price over the last 12 months was AED 29,049 per square meter (AED 2,699 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in City Walk
- Verve City Walk City Walk · Citywalk Residential 1 13.71%Planned completion Sep 15, 2028
- Central Park Plaza City Walk · Citywalk Residential 1 43.68%Planned Oct 8, 2026, 30 days ago
- City Walk Crestlane 4 City Walk · Citywalk Residential 1 0.01%Planned completion Apr 25, 2030
- City Walk Crestlane 2 City Walk · Citywalk Residential 1 6.83%Planned completion Dec 10, 2028
- City Walk Crestlane 1 City Walk · Citywalk Residential 1 0.19%Planned completion Sep 30, 2029
- City Walk Crestlane 3 City Walk · Citywalk Residential 1 4.59%Planned completion Dec 10, 2028