45.05%complete

Clearpoint

Clearpoint is a building project in Mina Rashid, Dubai, by Mina Rashid Properties. The Dubai Land Department's register puts it at 45.05% complete.

The register gives no planned completion date for this project.

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2743), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
45.05%, as published by the Dubai Land Department
Construction start
Nov 9, 2023
Units
478
Buildings
3
Developer
Mina Rashid Properties
Community
Mina Rashid, in DLD's area Madinat Dubai Almelaheyah
Escrow bank
Emirates NBD Bank
DLD project number
2743

The register describes it as: "Bldg1:- G+10+R, Bldg2:- G+10+R, Bldg3:- G+10+R Residential.The project designed to have a concrete structure and block with internal and external finishes."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202645.05%

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

522 off-plan sales in Clearpoint have been registered with the Dubai Land Department, worth AED 1.14 billion in all, the first on Sep 29, 2023 and the latest on Nov 5, 2026. 7 of them in the last 90 days. The median price over the last 12 months was AED 19,539 per square meter (AED 1,815 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.

More in Mina Rashid