Damac Bay 2
Damac Bay 2 is a building project in Dubai Harbour, Dubai, by Damac Mdn Investment. The Dubai Land Department's register puts it at 30.3% complete.
The register gives no planned completion date for this project.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2644), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 30.3%, as published by the Dubai Land Department
- Construction start
- Jul 1, 2023
- Units
- 646
- Buildings
- 2
- Developer
- Damac Mdn Investment
- Master developer
- Harbour Properties
- Community
- Dubai Harbour, in DLD's area Marsa Dubai
- Escrow bank
- Emirates NBD Bank
- DLD project number
- 2644
The register describes it as: "2 Towers of B+G+4P+25,Residential+Retail.The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 30.3% |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
630 off-plan sales in Damac Bay 2 have been registered with the Dubai Land Department, worth AED 3.41 billion in all, the first on Oct 11, 2023 and the latest on Aug 17, 2026. 1 of them in the last 90 days. The median price over the last 12 months was AED 46,510 per square meter (AED 4,321 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Dubai Harbour
- Damac Bay Dubai Harbour · Damac 33.76%Planned completion Jan 15, 2027
- Palace by the Beach Dubai Harbour · Emaar 0%Planned completion Nov 30, 2031
- Bayview Dubai Harbour · Emaar 63.02%Planned completion Jul 31, 2028
- Seapoint Dubai Harbour · Emaar 36.78%Planned completion Mar 31, 2028
- W Residences at Dubai Harbour Dubai Harbour · Arada 3.99%Planned completion Dec 31, 2028
- Sobha Seahaven Tower B & C Dubai Harbour · Sobha 40.2%Planned completion Oct 31, 2028
More by Damac
- Aykon City 3 Business Bay · Damac 31.35%Planned completion Dec 30, 2027
- Damac District Damac Hills · Damac 4.07%Planned completion Mar 30, 2029
- Chelsea Residences 2 by Damac Dubai Maritime City · Damac 5.44%Planned completion Dec 31, 2029
- Damac Riverside Views - Capri 1 Dubai Investment Park Second · Damac 8.18%Planned completion Mar 31, 2029
- Damac Riverside Views - Azure 2 Dubai Investment Park Second · Damac 5.8%Planned completion Mar 31, 2029
- Chelsea Residences by Damac Dubai Maritime City · Damac 5.19%Planned completion Dec 31, 2029