21.69%complete

Damac Hills (2) - Park Greens 1

Damac Hills (2) - Park Greens 1 is a villa project in Damac Hills 2, Dubai, by Front Line Investment Management. The Dubai Land Department's register puts it at 21.69% complete, with planned completion on Mar 30, 2027.

Planned completion: Mar 30, 2027. Time left: 5 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2859), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
21.69%, as published by the Dubai Land Department
Planned completion
Mar 30, 2027
Construction start
Feb 18, 2024
Developer
Front Line Investment Management
Community
Damac Hills 2, in DLD's area Madinat Hind 4
Escrow bank
First Abu Dhabi Bank
DLD project number
2859

The register describes it as: "216 G+1+R ,Residential Townhouses.The project designed to have a concrete structure and block with internal and external finishes."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202621.69%Mar 30, 2027

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.