95.19%complete

Damac Hills (2) - Violet

Damac Hills (2) - Violet is a villa project in Damac Hills 2, Dubai, by Front Line Investment Management. The Dubai Land Department's register puts it at 95.19% complete.

The register gives no planned completion date for this project.

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2734), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
95.19%, as published by the Dubai Land Department
Construction start
Oct 23, 2023
Developer
Front Line Investment Management
Community
Damac Hills 2, in DLD's area Madinat Hind 4
Escrow bank
Emirates NBD Bank
DLD project number
2734

The register describes it as: "526 Nos. G+1+R Villas Villas , The project designed to have a concrete structure and block with internal and external finishes."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202695.19%

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.