Damac Riverside Views - Marine 2 is a building project in Dubai Investment Park Second, Dubai, by Damac Mry Investment. The Dubai Land Department's register puts it at 12.02% complete, with planned completion on May 31, 2028.
Planned completion: May 31, 2028. Time left: 1 year 7 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3373), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 12.02%, as published by the Dubai Land Department
- Planned completion
- May 31, 2028
- Construction start
- Jan 29, 2025
- Units
- 358
- Buildings
- 2
- Developer
- Damac Mry Investment
- Community
- Dubai Investment Park Second
- Escrow bank
- First Abu Dhabi Bank
- DLD project number
- 3373
The register describes it as: "Project consists of G+3P+14+R residential building located in Dubai Investment Park second, Dubai. The building is designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 12.02% | May 31, 2028 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
278 off-plan sales in Damac Riverside Views - Marine 2 have been registered with the Dubai Land Department, worth AED 364 million in all, the first on Jul 7, 2025 and the latest on Oct 29, 2026. 8 of them in the last 90 days. The median price over the last 12 months was AED 15,464 per square meter (AED 1,437 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Dubai Investment Park Second
- Damac Riverside Views - Capri 1 Dubai Investment Park Second · Damac 8.18%Planned completion Mar 31, 2029
- Damac Riverside Views - Azure 2 Dubai Investment Park Second · Damac 5.8%Planned completion Mar 31, 2029
- Damac Riverside Views - Capri 2 Dubai Investment Park Second · Damac 8.33%Planned completion Mar 31, 2029
- Damac Riverside Views - Indigo 1 Dubai Investment Park Second · Damac 12.13%Planned completion Mar 31, 2029
- Damac Riverside Views - Royal 3&4 Dubai Investment Park Second · Damac 13.36%Planned completion Mar 31, 2029
- Damac Riverside Views - Indigo 2 Dubai Investment Park Second · Damac 12%Planned completion Mar 31, 2029
More by Damac
- Aykon City 3 Business Bay · Damac 31.35%Planned completion Dec 30, 2027
- Damac District Damac Hills · Damac 4.07%Planned completion Mar 30, 2029
- Damac Bay Dubai Harbour · Damac 33.76%Planned completion Jan 15, 2027
- Chelsea Residences 2 by Damac Dubai Maritime City · Damac 5.44%Planned completion Dec 31, 2029
- Chelsea Residences by Damac Dubai Maritime City · Damac 5.19%Planned completion Dec 31, 2029
- Damac Bay 2 Dubai Harbour · Damac 30.3%No planned date in the register