54.7%complete

Edgewater Residences 2

Edgewater Residences 2 is a building project in Palm Deira, Dubai, by M G S Development. The Dubai Land Department's register puts it at 54.7% complete, with planned completion on Aug 31, 2026.

Planned completion was Aug 31, 2026. Time since: 2 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3011), which also shows the latest inspection date and photos.

Facts

Status
Past planned completion
Official progress
54.7%, as published by the Dubai Land Department
Planned completion
Aug 31, 2026
Construction start
Jun 30, 2024
Units
97
Buildings
1
Developer
M G S Development
Master developer
Nakheel .(P J S C)
Community
Palm Deira
Escrow bank
Abu Dhabi Commercial Bank
DLD project number
3011

The register describes it as: "G+2P+12TYP+R Residential Building."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202654.7%Aug 31, 2026

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

88 off-plan sales in Edgewater Residences 2 have been registered with the Dubai Land Department, worth AED 215 million in all, the first on Oct 8, 2024 and the latest on Oct 13, 2026. 1 of them in the last 90 days. The median price over the last 12 months was AED 24,701 per square meter (AED 2,295 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.

More in Palm Deira

More by M G S Development