Ellington House

Ellington House is a building project in Dubai Hills Estate, Dubai, by Epd Development. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Feb 28, 2025.

Completed on Feb 28, 2025, against a planned date of Feb 28, 2025.

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2439), which also shows the latest inspection date and photos.

Facts

Status
Completed
Official progress
100%, as published by the Dubai Land Department
Planned completion
Feb 28, 2025
Construction start
Jul 7, 2022
Units
150
Buildings
1
Developer
Epd Development
Master developer
Dubai Hills Estate
Community
Dubai Hills Estate, in DLD's area Hadaeq Sheikh Mohammed Bin Rashid
Escrow bank
Abu Dhabi Commercial Bank
DLD project number
2439

The register describes it as: "1 residential Building : G + 1P + 12F + R.The project designed to have a concrete structure and block with internal and external finishes."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 2026100%Feb 28, 2025

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

193 off-plan sales in Ellington House have been registered with the Dubai Land Department, worth AED 456 million in all, the first on Sep 27, 2022 and the latest on Jul 10, 2025.

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.