10%complete

Vida Residences Hillside

Vida Residences Hillside is a building project in Dubai Hills Estate, Dubai, by Dubai Hills Estate. The Dubai Land Department's register puts it at 10% complete, with planned completion on May 31, 2029.

Planned completion: May 31, 2029. Time left: 2 years 7 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3534), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
10%, as published by the Dubai Land Department
Planned completion
May 31, 2029
Construction start
Jun 30, 2025
Units
500
Buildings
3
Developer
Dubai Hills Estate
Community
Dubai Hills Estate, in DLD's area Hadaeq Sheikh Mohammed Bin Rashid
Escrow bank
Emirates Islamic Bank
DLD project number
3534

The register describes it as: "Shared: (1B+G+1P++1F+R) ; Tower A: G+20F+R ; Tower B: G+19F+R"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202610%May 31, 2029

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

451 off-plan sales in Vida Residences Hillside have been registered with the Dubai Land Department, worth AED 1.27 billion in all, the first on Jun 24, 2025 and the latest on Oct 23, 2026. 26 of them in the last 90 days. The median price over the last 12 months was AED 26,802 per square meter (AED 2,490 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.