100%complete

Ellington House III

Ellington House III is a building project in Dubai Hills Estate, Dubai, by Eh 3 Development. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Jul 31, 2025.

Completed on Jul 30, 2026, against a planned date of Jul 31, 2025.

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2581), which also shows the latest inspection date and photos.

Facts

Status
Completed
Official progress
100%, as published by the Dubai Land Department
Planned completion
Jul 31, 2025
Construction start
Feb 7, 2023
Units
110
Buildings
1
Developer
Eh 3 Development
Master developer
Dubai Hills Estate
Community
Dubai Hills Estate, in DLD's area Hadaeq Sheikh Mohammed Bin Rashid
Escrow bank
Abu Dhabi Commercial Bank
DLD project number
2581

The register describes it as: "Residential Building (G+1P+9F+R).The project designed to have a concrete structure and block with internal and external finishes."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 2026100%Jul 31, 2025

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

124 off-plan sales in Ellington House III have been registered with the Dubai Land Department, worth AED 332 million in all, the first on May 17, 2023 and the latest on Mar 27, 2026. The median price over the last 12 months was AED 25,779 per square meter (AED 2,395 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.

More in Dubai Hills Estate