Elmora
Elmora is a building project in Jumeirah Garden City, Dubai, by Neoterra Real Estate Development. The Dubai Land Department's register puts it at 0.04% complete (not started), with planned completion on Feb 15, 2028.
Planned completion: Feb 15, 2028. Time left: 1 year 3 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 4088), which also shows the latest inspection date and photos.
Facts
- Status
- Not started
- Official progress
- 0.04%, as published by the Dubai Land Department
- Planned completion
- Feb 15, 2028
- Construction start
- Dec 15, 2025
- Units
- 85
- Buildings
- 1
- Developer
- Neoterra Real Estate Development
- Master developer
- Meraas Estates
- Community
- Jumeirah Garden City, in DLD's area Al Satwa
- DLD project number
- 4088
The register describes it as: "G+2P+8 RESIDENTIAL BUILDING"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 0.04% | Feb 15, 2028 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
48 off-plan sales in Elmora have been registered with the Dubai Land Department, worth AED 66 million in all, the first on Jan 30, 2026 and the latest on Jul 6, 2026. The median price over the last 12 months was AED 30,089 per square meter (AED 2,795 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Jumeirah Garden City
- Villea West Jumeirah Garden City · Palmridge Real Estate Development 4.06%Planned completion Nov 1, 2027
- Jad 288 Jumeirah Garden City · Jad Global Real Estate Development 1.88%Planned completion Dec 31, 2027
- Evergrin House Jumeirah Garden City · OBJ1 Real Estate Development 54.54%Planned Jun 30, 2026, 4 months ago
- Holm One Jumeirah Garden City · Holm Avenue Real Estate Development 17.71%Planned completion Mar 30, 2028
- Vibe Jumeirah Garden City · Arsenal East Real Estate Development 1.49%Planned completion Aug 31, 2028
- Linea by Holm Jumeirah Garden City · Holm Avenue Real Estate Development 0.69%Planned completion Jun 15, 2028