Equiti Gates
Equiti Gates is a building project in Down Town Jabal Ali, Dubai, by B N H Real Estate Developer. The Dubai Land Department's register puts it at 100% complete (completed).
Completed on Oct 21, 2025.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2839), which also shows the latest inspection date and photos.
Facts
- Status
- Completed
- Official progress
- 100%, as published by the Dubai Land Department
- Construction start
- Oct 6, 2022
- Units
- 284
- Buildings
- 1
- Developer
- B N H Real Estate Developer
- Master developer
- Nakheel .(P J S C)
- Community
- Down Town Jabal Ali, in DLD's area Jabal Ali Industrial Second
- Escrow bank
- Abu Dhabi Commercial Bank
- DLD project number
- 2839
The register describes it as: "B+G+3P+14+R Residential+Retail,The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 100% |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
244 off-plan sales in Equiti Gates have been registered with the Dubai Land Department, worth AED 206 million in all, the first on Jun 4, 2024 and the latest on Jan 21, 2026. The median price over the last 12 months was AED 15,658 per square meter (AED 1,455 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Down Town Jabal Ali
- Eleve by Deyaar Down Town Jabal Ali · Deyaar 20.01%No planned date in the register
- Arian by Azizi Down Town Jabal Ali · Azizi 2%Planned completion Jan 16, 2028
- Azizi Wares Down Town Jabal Ali · Azizi 2%Planned completion Mar 4, 2028
- Samana Business Hub Down Town Jabal Ali · Samana 0.8%Planned completion Sep 30, 2029
- Peace Avenue by Peace Homes Down Town Jabal Ali · Peace Homes 3.52%Planned completion Jan 31, 2029